Playground Progress

Day 2 – 9th January

Temporary fencing has been erected as the contractor’s crew moved in to dismantle the old playground whilst carefully retaining those elements we are keeping like the beloved train, trees and hopefully the honeysuckle over the arches.

Day 13 – 20th January

The Playground starts to take shape with the frames for the basket swing, climbing frame and hexagon swing in place.

Day 26 – 2nd February 2019

Installation has been progressing well, despite a short break for the snow!

The Extron climbing frame with spiral slide, behind the frame for the nest swing and the trampoline.

The toddler Dom play unit with slide.

One end of the dual cableway.

The six pieces of gym equipment, two of the round tables with benches and the other end of the cable way in the distance.

Day 37 – 13th February 2019

Six pieces of gym equipment with grass grow through matting are now complete.

Whilst some of the playground and gym equipment is looking fit for use, please note that until the contractors fences are removed, the equipment has not been checked and signed off, so not necessarily fit for purpose.

We respectfully ask all those not involved with the construction to stay out of the contractors area until the fences are removed.

Seated Leg Press and Parallel Bars
Leg Lift and Chin Up Station with Double Air Walker
Horizontal Ladder and Arm and Pedal Bike

Day 40 – 16th February 2019 – Mounds and Compensation

There are four new mounds in the play area that must be compensated for, for the loss of flood plain capacity they remove. This compensation ensures the recreation ground can take the same amount of flood water as before the playground was constructed.

Two of the new mounds pictured above, the one with the play tube will be covered in artificial grass.

Above are the remaining two new mounds in the background. Both mounds turfed and awaiting a wobbly bridge to join them. The frame for the High Rocker is in the foreground.

Above is one of the two areas where soil has been removed to compensate for flood capacity, the soil being used to form the mounds. This area is near the boundary with SODC – the highest part of the sight to compensate for the upper parts of the mounds.

The recesses are approximately 200mm deep. The edges are to be tapered and area grass seeded.

The second compensation area (pictured above) is situated on the far side of the recreation ground where the levels are nearly the same as the lower parts of the mounds.

New Playground – update November 2018

It is with great thanks from the following providers that we have secured the necessary funds to proceed with the project to update the Playground and add a new Outdoor Gym.

SODC                                                                                                                   £99,790

WREN’s FCC Community Action Fund                                                 £80,040

ACTIVE SPACES *                                                                                          £5,000

Agrivert                                                                                                               £500

Howbery Park                                                                                                   £300

Waitrose                                                                                                             £240

Homebase Property Management                                                          £150

There are also contributions of £513 from the community donated in memory of the former Parish Council Chairman John Bellamy.

In addition Crowmarsh Parish Council is contributing to the project a sum of approximately £35,000.  This includes £8604 to FCC Recycling UK Ltd to facilitate the WREN grant.

With a total of £185,000 worth of grants from our three main funding providers Crowmarsh Parish Council is now planning the commencement of the project.  Due diligence has been carried out and Eibe has been appointed contractor for the New Playground and Outdoor Gym Installation.

Dates to Remember: Crowmarsh Playground closed from 8th January until approximately Easter 2019

Work is scheduled to commence on the 8th January with an estimated handover mid to late March – therefore the playground and surrounding area will be off limits during this time.

Plans are currently in place to commence work on the 8th January with an estimated handover mid to late March – therefore the playground and surrounding area will be off limits for this time.

We look forward to being able to welcome you all back to the New Playground and New Outdoor Gym with a Grand Opening around Easter.

Crowmarsh Parish Council

Crowmarsh Playground Plan

*ACTIVE SPACES (The London Marathon Charitable Trust and Fields Trust)

New playground update – 20 September 2018

FUNDING SECURED

Subject to legal requirements Crowmarsh Parish Council is happy to report that sufficient funding has been secured such that the New Playground and Outdoor Gym project can go ahead.

Many thanks to the providers, SODC, WREN’s FCC Community Action Fund and ACTIVE SPACES (The London Marathon Charitable Trust and Fields Trust) for their contributions, and thanks to the community for your letters of support and feedback helping to shape the project and its outcome.

We look forward to sharing more with you in the near future once we have gone through due diligence and appointed a contractor.

Crowmarsh Parish Council

Local Neighbourhood Plan discussion meetings

The Steering Group responsible for developing your Crowmarsh Parish Neighbourhood Plan is hosting meetings at Crowmarsh Gifford School on Tuesday 13 March and North Stoke Village Hall on Thursday 15 March, both starting at 7.30 pm. The purpose of the meetings is to explain what has been achieved so far and to put the preliminary findings to you for discussion and informal consultation.